Exit 2 Area

Exit 2 Interchange and Mainline
Contract 13933E has reconstructed and widened the NB and SB barrels of I-93 in the area of Exit 2, reconstructed NB & SB Exit 2 ramps, reconfiguring the SB ramps from cloverleaf to diamond-type design, replaced the NB & SB I-93 bridges over Pelham Road, and reconstructed a portion of Pelham Road. This project was awarded to George R. Cairns & Sons, Inc. for a bid price of $40.9M on July 11, 2012 and was completed in November 2015.